Project Planning
- Preconstruction budget and schedule review
- Permitting, inspections and owner reviews tracked to closeout
- Specialty trade partners scheduled, coordinated and supervised by our superintendent
- Closeout records, warranties and as-built drawings delivered with the building
A warehouse floor is judged by a forklift, not by a person walking across it. The operator feels every ridge and low spot through the mast, and a floor that looks perfectly good to an owner on a walkthrough can slow a very narrow aisle to a crawl. For that reason a commercial slab is never just a pour. It is a controlled sequence of subgrade work, reinforcement, placement, finishing, curing and joint cutting, and the decisions made in each step show up for as long as the building stands.
New Mexico adds its own wrinkles. Air is dry, wind is common, and a slab placed on a clear afternoon can lose surface moisture faster than a finisher can bring up cream. Soils under the slab range from stable gravel to clay that moves with moisture. Temperature swings between day and night are wide enough to crack a restrained slab that was not given enough joints.
We build floors for distribution centers, food plants, shops, showrooms and hangars, and treat the slab as the piece of equipment it is. Below is how we think through each part of the work.
Planning the pour before the trucks arrive
We begin with the owner's use. Rack loads, forklift types, wheel hardness, aisle widths, process equipment and washdown needs all feed the floor specification. A very narrow aisle warehouse asks for a much tighter flatness and levelness tolerance than a retail stockroom, and a slab with floor drains and chemical exposure needs a different surface than a dry storage floor. Getting that conversation done in preconstruction saves expensive grinding later.
Then we plan the pour itself: the placement sequence, the screed method, the number of crews, the finishing equipment and the curing plan. Large slabs are poured in strips or checkerboard patterns with a laser-guided screed where the specification calls for it, and joints are located to match the column grid and the racking layout. The goal is a floor that is flat where it has to be, that cracks where it is meant to, and that cures slowly and evenly.
Subgrade to sealed surface
A slab begins with the subgrade. We proof-roll and compact the base, place the specified granular layer and, where a vapor retarder is required, install it with lapped and taped seams and protect it from punctures. Reinforcing steel or fibers go in according to the structural design, with dowels at construction joints so adjoining panels share load. Embedded items, floor drains and trench drains are set to elevation before the concrete arrives.
During placement the crew consolidates, screeds, floats and trowels the surface in the right window, which varies with temperature, wind and mix. Sawcutting follows at the right time, usually the next morning, to control cracking, and the joints are later filled with a semi-rigid filler where forklift traffic will cross them. We coordinate the floor work with the foundation scope so the elevations, the edge details and the pour sequence line up.
Floors for different kinds of buildings
A food processing plant needs sloped floors with drains, sealed or coated surfaces and joints that resist washdown. Roswell, for example, hosts one of the world's largest mozzarella factories operated by Leprino Foods, and in Clovis, Southwest Cheese announced a $140 million expansion that was expected to raise operating capacity by 30 percent. Plants like these live and die by a floor that can be cleaned and that stays sound under thermal shock, and they are why we are comfortable with food and beverage processing slabs.
Distribution and fulfillment buildings ask for flatness, wear resistance and joint durability; our work in fulfillment and logistics centers is built around that. Freezers and coolers require insulated, heated slabs that keep the subgrade from freezing, a topic we cover under cold storage construction. Light industrial shops and aircraft hangars need floors with specific load ratings and often a hardened surface.
Moisture, curl and the quiet problems
Three issues cause most floor complaints. The first is moisture: if the slab will receive a coating, resilient flooring or a sealed finish, we test its moisture condition before installation and plan mitigation when readings are high. The second is curl, in which the top of the slab dries faster than the bottom and the panel edges lift. A well-designed mix, proper curing and sensible joint spacing keep curl in check. The third is cracking from restraint, which is why we isolate the slab from columns and walls with the details shown on the drawings.
Dry desert air raises the risk of plastic shrinkage cracking, so we use windbreaks, fogging, evaporation retarders and quick curing to protect the surface during finishing. Concrete deliveries are scheduled in the cooler hours for summer pours. None of these steps is fancy. They simply have to be done every time.
Specification, testing and the code frame
Floor specifications typically define flatness and levelness numbers, compressive strength, aggregate and cement content, shrinkage limits and the curing method. We measure flatness within the window the specification allows, usually within 72 hours of placement, so any needed correction occurs while the owner still has leverage. Cylinders are cast and broken by a third-party testing agency.
The slab is part of the building and falls under the same state code as the walls. The 2021 New Mexico Commercial Building Code, 14.7.2 NMAC, adopts the 2021 International Building Code as amended and took effect July 14, 2023. Under it the structural engineer's drawings and special inspection program govern. Energy rules matter for slabs too: the 2021 New Mexico Commercial Energy Conservation Code took effect January 30, 2024 and affects insulation at slab edges and under heated floors.
Where floor money goes
Thickness, reinforcement and the flatness specification are the big drivers. A slab that must meet very tight tolerances needs better equipment, more skilled finishers and often a shorter placement strip, all of which cost money. Post-tensioning and hardened surfaces add cost as well. Smaller drivers include joint filler, curing and sealers.
Owners in logistics and distribution sometimes spend heavily on flatness and later find their equipment does not need it. We help them match the specification to the truck fleet and racking, and we price alternatives so the decision is informed. A modest change in tolerance can pay for itself in the slab cost without affecting daily operations.
Match the slab to the work it will carry
Tell us what will roll across the floor and we will help you set the thickness, tolerance and joint layout that fit.
Questions Owners Ask
How flat does a warehouse floor need to be?
It depends on the equipment. Very narrow aisle trucks and automated vehicles need tight flatness and levelness numbers, while a standard reach-truck warehouse can accept looser tolerances. The racking supplier and equipment manufacturer provide the requirement, and the specification is written to match.
Why do slabs crack and can it be prevented entirely?
Concrete shrinks as it cures, and restrained shrinkage causes cracks. Joints, proper curing and reinforcement control where and how much, but no commercial slab is guaranteed crack free. The goal is to keep cracks tight and at joints where they do no harm.
Can you pour a slab in the heat of summer?
Yes, with planning. We schedule deliveries early, cool the mix when needed, use shade and fogging and cure quickly. Hot, dry, windy conditions require extra attention, and we will sometimes stop a pour if conditions are beyond control.
How soon can forklifts and racking use the new floor?
Light traffic can start after several days, but full loading should wait until the concrete reaches the design strength, commonly 28 days, unless the engineer approves earlier use. We work with the owner to coordinate racking installation and move-in around that curing period.
What does a floor in a cold storage building do differently?
The slab sits over insulation and underfloor heating or ventilation to prevent the ground from freezing and heaving the floor. The details are coordinated among the structural, refrigeration and civil designers, and it is among the most demanding slab assemblies we build.
Do you recommend sealers or hardeners?
Often yes for warehouses and shops: a densifier and sealer reduce dusting and make cleaning easier, and a hardener helps with heavy wear. We recommend them based on the traffic and the owner's maintenance plan.